{"id":2243,"date":"2023-06-30T12:00:00","date_gmt":"2023-06-30T12:00:00","guid":{"rendered":"https:\/\/pfs.naoj.org\/blog\/?p=2243"},"modified":"2023-06-26T17:58:25","modified_gmt":"2023-06-26T17:58:25","slug":"installation-of-the-pfs-fiber-cable-was-completed","status":"publish","type":"post","link":"https:\/\/pfs.naoj.org\/blog\/2023\/06\/p2243","title":{"rendered":"Installation of the PFS fiber cable was completed!"},"content":{"rendered":"\n<p>We achieved one milestone in early June 2023. The installation of all the fiber cables has been completed finally!<\/p>\n\n\n\n<p>Among the PFS instruments, the fiber cable system, which consists of about 2400 optical fibers, delivers the light from the prime focus of the Subaru telescope to the Spectrograph Modules. The fiber cables are assembled into four units, each of which is used for one Spectrograph Module. <\/p>\n\n\n<div class=\"wp-block-image\">\n<figure class=\"aligncenter size-large is-resized\"><a href=\"https:\/\/pfs.naoj.org\/blog\/wp-content\/uploads\/2023\/06\/CableB_schematic_on_telescope_v2.png\"><img loading=\"lazy\" decoding=\"async\" src=\"https:\/\/pfs.naoj.org\/blog\/wp-content\/uploads\/2023\/06\/CableB_schematic_on_telescope_v2-1024x705.png\" alt=\"\" class=\"wp-image-2248\" width=\"512\" height=\"353\" srcset=\"https:\/\/pfs.naoj.org\/blog\/wp-content\/uploads\/2023\/06\/CableB_schematic_on_telescope_v2-1024x705.png 1024w, https:\/\/pfs.naoj.org\/blog\/wp-content\/uploads\/2023\/06\/CableB_schematic_on_telescope_v2-300x207.png 300w, https:\/\/pfs.naoj.org\/blog\/wp-content\/uploads\/2023\/06\/CableB_schematic_on_telescope_v2-768x529.png 768w, https:\/\/pfs.naoj.org\/blog\/wp-content\/uploads\/2023\/06\/CableB_schematic_on_telescope_v2-624x430.png 624w, https:\/\/pfs.naoj.org\/blog\/wp-content\/uploads\/2023\/06\/CableB_schematic_on_telescope_v2.png 1500w\" sizes=\"auto, (max-width: 512px) 100vw, 512px\" \/><\/a><\/figure><\/div>\n\n\n<p>The fiber cable system was developed by Laborat\u00f3rio Nacional de Astrof\u00edsica and Kavli IPMU in collaboration with Durham University. All four units were delivered to Subaru Telescope by June 2022. After it, we have been arranging installation of the fiber cables. <a rel=\"noreferrer noopener\" href=\"https:\/\/pfs.naoj.org\/blog\/2023\/03\/p2170\" target=\"_blank\">The third cable was installed<\/a> in February 2023, and the forth in June 2023.<\/p>\n\n\n\n<p>As we did for the previous three cables, we installed the fiber cable in two stages. On the first day, the fiber was routed from the prime focus of the telescope to the bottom of the telescope (see the blue star in the above figure). On the second day, the rest of the fiber cable was pulled up to the fourth floor, where the Spectrograph Modules are installed. If the fiber got twisted and\/or stressed, the image quality of out-coming light to the spectrograph degraded. To avoid this, the fiber cable was installed carefully checking its orientation (see this article for details).<\/p>\n\n\n\n<p>About 10 people from Subaru DayCrews and the PFS team worked on the installation. The team&#8217;s cooperation at various positions was crucial for routing such a long (&gt;50 m) cable.<\/p>\n\n\n\n<div class=\"wp-block-columns is-layout-flex wp-container-core-columns-is-layout-9d6595d7 wp-block-columns-is-layout-flex\">\n<div class=\"wp-block-column is-layout-flow wp-block-column-is-layout-flow\" style=\"flex-basis:50%\">\n<figure class=\"wp-block-image size-large\"><a href=\"https:\/\/pfs.naoj.org\/blog\/wp-content\/uploads\/2023\/06\/CableB4_telescope.png\"><img loading=\"lazy\" decoding=\"async\" width=\"1024\" height=\"802\" src=\"https:\/\/pfs.naoj.org\/blog\/wp-content\/uploads\/2023\/06\/CableB4_telescope-1024x802.png\" alt=\"\" class=\"wp-image-2246\" srcset=\"https:\/\/pfs.naoj.org\/blog\/wp-content\/uploads\/2023\/06\/CableB4_telescope-1024x802.png 1024w, https:\/\/pfs.naoj.org\/blog\/wp-content\/uploads\/2023\/06\/CableB4_telescope-300x235.png 300w, https:\/\/pfs.naoj.org\/blog\/wp-content\/uploads\/2023\/06\/CableB4_telescope-768x601.png 768w, https:\/\/pfs.naoj.org\/blog\/wp-content\/uploads\/2023\/06\/CableB4_telescope-624x488.png 624w, https:\/\/pfs.naoj.org\/blog\/wp-content\/uploads\/2023\/06\/CableB4_telescope.png 1100w\" sizes=\"auto, (max-width: 1024px) 100vw, 1024px\" \/><\/a><figcaption>Day 1: installing the fiber cable on the telescope<\/figcaption><\/figure>\n<\/div>\n\n\n\n<div class=\"wp-block-column is-vertically-aligned-center is-layout-flow wp-block-column-is-layout-flow\" style=\"flex-basis:70%\">\n<figure class=\"wp-block-image size-large\"><a href=\"https:\/\/pfs.naoj.org\/blog\/wp-content\/uploads\/2023\/06\/CableB4_dome.png\"><img loading=\"lazy\" decoding=\"async\" width=\"1024\" height=\"422\" src=\"https:\/\/pfs.naoj.org\/blog\/wp-content\/uploads\/2023\/06\/CableB4_dome-1024x422.png\" alt=\"\" class=\"wp-image-2245\" srcset=\"https:\/\/pfs.naoj.org\/blog\/wp-content\/uploads\/2023\/06\/CableB4_dome-1024x422.png 1024w, https:\/\/pfs.naoj.org\/blog\/wp-content\/uploads\/2023\/06\/CableB4_dome-300x124.png 300w, https:\/\/pfs.naoj.org\/blog\/wp-content\/uploads\/2023\/06\/CableB4_dome-768x316.png 768w, https:\/\/pfs.naoj.org\/blog\/wp-content\/uploads\/2023\/06\/CableB4_dome-624x257.png 624w, https:\/\/pfs.naoj.org\/blog\/wp-content\/uploads\/2023\/06\/CableB4_dome.png 1500w\" sizes=\"auto, (max-width: 1024px) 100vw, 1024px\" \/><\/a><figcaption>Day 2: pulling up the fiber cable<\/figcaption><\/figure>\n<\/div>\n<\/div>\n\n\n\n<p>Monitoring the fiber image after installation suggested that the fiber cable had some stress. Therefore, routing was adjusted in late June. We are monitoring the fiber to see if the adjustment has worked.<\/p>\n\n\n\n<p>P.S. It snowed a little when we installed the fiber cable at the end of May..<\/p>\n\n\n<div class=\"wp-block-image\">\n<figure class=\"aligncenter size-large is-resized\"><a href=\"https:\/\/pfs.naoj.org\/blog\/wp-content\/uploads\/2023\/06\/CableB4_DSC02988.jpg\"><img loading=\"lazy\" decoding=\"async\" src=\"https:\/\/pfs.naoj.org\/blog\/wp-content\/uploads\/2023\/06\/CableB4_DSC02988-1024x683.jpg\" alt=\"\" class=\"wp-image-2244\" width=\"256\" height=\"171\" srcset=\"https:\/\/pfs.naoj.org\/blog\/wp-content\/uploads\/2023\/06\/CableB4_DSC02988-1024x683.jpg 1024w, https:\/\/pfs.naoj.org\/blog\/wp-content\/uploads\/2023\/06\/CableB4_DSC02988-300x200.jpg 300w, https:\/\/pfs.naoj.org\/blog\/wp-content\/uploads\/2023\/06\/CableB4_DSC02988-768x512.jpg 768w, https:\/\/pfs.naoj.org\/blog\/wp-content\/uploads\/2023\/06\/CableB4_DSC02988-624x416.jpg 624w, https:\/\/pfs.naoj.org\/blog\/wp-content\/uploads\/2023\/06\/CableB4_DSC02988.jpg 1500w\" sizes=\"auto, (max-width: 256px) 100vw, 256px\" \/><\/a><\/figure><\/div>","protected":false},"excerpt":{"rendered":"<p>We achieved one milestone in early June 2023. The installation of all the fiber cables has been completed finally! Among the PFS instruments, the fiber cable system, which consists of about 2400 optical fibers, delivers the light from the prime focus of the Subaru telescope to the Spectrograph Modules. The fiber cables are assembled into four units, each of which&#8230; <a href=\"https:\/\/pfs.naoj.org\/blog\/2023\/06\/p2243\">Read more &raquo;<\/a><\/p>\n","protected":false},"author":3,"featured_media":2247,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"_locale":"en_US","_original_post":"2243","footnotes":""},"categories":[2],"tags":[33,22,9],"class_list":["post-2243","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-development","tag-ait","tag-fiber-cable","tag-subaru","en-US"],"_links":{"self":[{"href":"https:\/\/pfs.naoj.org\/blog\/wp-json\/wp\/v2\/posts\/2243","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/pfs.naoj.org\/blog\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/pfs.naoj.org\/blog\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/pfs.naoj.org\/blog\/wp-json\/wp\/v2\/users\/3"}],"replies":[{"embeddable":true,"href":"https:\/\/pfs.naoj.org\/blog\/wp-json\/wp\/v2\/comments?post=2243"}],"version-history":[{"count":4,"href":"https:\/\/pfs.naoj.org\/blog\/wp-json\/wp\/v2\/posts\/2243\/revisions"}],"predecessor-version":[{"id":2256,"href":"https:\/\/pfs.naoj.org\/blog\/wp-json\/wp\/v2\/posts\/2243\/revisions\/2256"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/pfs.naoj.org\/blog\/wp-json\/wp\/v2\/media\/2247"}],"wp:attachment":[{"href":"https:\/\/pfs.naoj.org\/blog\/wp-json\/wp\/v2\/media?parent=2243"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/pfs.naoj.org\/blog\/wp-json\/wp\/v2\/categories?post=2243"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/pfs.naoj.org\/blog\/wp-json\/wp\/v2\/tags?post=2243"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}